Steel For Fuel N° 054 of 56 6 Jul 2026
Data centers need the grid — so we have to make the grid better
by Andy Lubershane, Partner and Head of Research, Energy Impact Partners
In this note
The question
If the grid cannot connect AI data centers fast enough, is building a power plant next to each one the way out?
The answer
No. Co-location is not a shortcut around the grid but a second hard project bolted onto the first, and it cannot scale to a national load shock. The faster route is to buy controllability instead of steel: enforceable curtailment terms, technologies that push more through existing wires, and above all distributed batteries in commercial buildings.
03The argument
Almost none of this post is Lubershane’s. He writes an introduction of about ten paragraphs and then cross-posts an essay by Tim Hade in full, and unlike other guest sections in this publication there is no handover back at the end, so everything from the first subheading onward is Hade’s, including his own numbered source list. Hade’s starting point is that the constraint on AI in 2026 is neither chips nor talent but the grid, and that what the grid keeps running out of is not generation but slack: spare transformer capacity, spare substation bays, spare thermal margin when a single element is out of service, spare time in equipment supply chains. That converts the question from how to build more power plants into how to build more power system capacity fast, and the two have different answers. It is a calendar problem rather than an ideological one, he argues: data centers are built on roughly an 18-month clock and bulk power equipment on a 50- to 80-month one.
The seductive answer is to stop waiting and bring your own power. Hade’s objection is not that co-location fails but that it is misdescribed. A grid connection is not a wire; it is access to a system supplying voltage stiffness, frequency stability, high fault current and inertia, so stepping behind the meter changes the physics and not merely the ownership. Data centers make that harder than most loads would, being dense in power electronics, drawing non-linear current, ramping fast and designed to be intolerant of disturbance, so an islanded system has to absorb harmonics, step loads, a lower and softer fault current that can blind protective devices, and the risk of one transient tripping everything at once. All solvable, none trivial. Announced megawatts are also not delivered megawatts, especially where the project is really three projects: a data center, a power plant, and the microgrid controls tying them together. Nor is it an unregulated lane, and he reads a federal rejection of an expanded co-located arrangement at a nuclear plant as a warning that the rules are being written in real time. His conclusion is deliberately bounded: co-location will work in some places, for firms that can execute power-plant-grade projects, and cannot be the only plan.
The load is not a fixed object either, and that is where the argument turns. Training clusters are large, concentrated and indifferent to latency, so they can be sited where land and transmission already are. Inference cannot be, because it has to sit near users, which pulls compute toward metro areas, distribution substations and congested feeders, exactly where equipment bottlenecks and permitting friction are worst. Inference is also spikier than training, and spiky load at a constrained node is not a job for slow thermal plants but for fast, controllable resources. So the practical question becomes how to energize a large load sooner without breaking reliability, and the answer forming in the market is to split first power from ultimate firm service: a load that accepts an enforceable operating envelope can be connected while upgrades catch up. But an envelope only works if flexibility exists on the other side of the contract, and a curtailment obligation is not by itself a strategy. Hence the toolkit of demand response, grid-enhancing technologies and distributed batteries, of which he rates batteries highest because they are modular, fast and placeable. Placeable is the load-bearing word: for interconnection, location is destiny, and a megawatt of flexibility at the constrained substation is worth more than ten far away. The scale then comes from large commercial buildings, the overlooked middle between millions of homes and a handful of megaprojects.
His last move is that the binding constraint is not technical at all. We know how to curtail load, deploy batteries and instrument lines; what is missing is whether institutions can value, verify and accept flexibility as a substitute for steel, with capacity accreditation for aggregated portfolios the hardest part. Federal rules have opened a market pathway for aggregations of distributed resources, but implementation is uneven and the difficult pieces, coordination with distribution utilities, telemetry standards and accreditation itself, are unfinished. The political argument is where he ends: the coalition for using the existing grid better is broader than the coalition for new corridors, and a hyperscaler funding batteries across local commercial buildings converts a permitting fight into a visible local benefit. The closing frame is a choice between fortified private islands, each solving its own problem, and a better shared grid built partly with the capital already pouring into AI.
04What you need to know first
- Distributed energy resources
- The definition Lubershane quotes in the introduction, without naming whose it is: loads, generators or storage on the distribution system or behind customer meters that can be influenced or managed to help balance supply and demand for electricity on the grid.
- Behind the meter, or co-location
- Generation built on the customer’s side of the utility connection, serving the data center directly rather than through the grid.
- Operating envelope
- A service in which a large load accepts caps, ramp limits, telemetry and defined curtailment rights in return for being energized sooner.
- Grid-enhancing technologies
- Equipment and software that raise the usable capacity of existing lines, such as dynamic line ratings, which set a line’s limit from actual weather rather than a fixed assumption.
05Details worth keeping
- The introduction is where the relationships sit: Lubershane’s own earlier essay on distributed energy, his firm’s investment in Hade’s company Brightfield Infrastructure, and Brightfield’s acquisition by Voltus. He also names ERock, formerly Enchanted Rock, as a longtime portfolio company now listed, and a Tesla, Sunrun and Renew Home collaboration on residential aggregation.
- Lubershane’s own view, offered in passing: off-grid data centers are compelling to him, especially if going off grid means tapping more low-cost solar, while space-based ones make no practical or economic sense and look like a marketing ploy.
- Hade’s worked example of the strategy: a 300 MW data center that can cap its net draw by 75 MW under defined conditions needs no 75 MW plant next door, and roughly 150 commercial sites each with a 500 kW four-hour battery would supply the same lever.
- His community argument: a data center offering a town few permanent jobs is not always a compelling pitch, while paying to harden local businesses and public buildings with batteries and backup capability is tangible, and converts opposition into a deal.
- Two of the essay’s 31 numbered sources are unpublished memos dated February 2026, one provided to the author and one described as prepared for the federal regulator. Several of the interconnection and flexibility claims rest on them.
- The post carries a single figure, captioned with a battery manufacturer’s November 2024 press-release headline about a commercial and industrial storage product. The note cannot see the image, and nothing in the argument depends on it.
06Claims worth citing
All figures as stated on 2026-07-06. Nearly all are Hade’s, citing outside reports; the load forecasts and equipment lead times move fastest.
- American data centers used about 176 terawatt-hours in 2023, roughly 4.4% of national electricity, projected at 325 to 580 terawatt-hours by 2028, or about 6.7% to 12%. Lawrence Berkeley National Laboratory, cited by Hade
- As average power that is roughly 20 gigawatts now and 37 to 66 gigawatts then, an increment of 17 to 46 gigawatts in about five years before arguing about peak. Hade’s arithmetic on the LBNL range
- Utilities’ five-year peak load growth forecasts rose from roughly 24 gigawatts to about 166 gigawatts over three years. Grid Strategies compilation, cited by Hade
- Large power transformer lead times run roughly 80 to 210 weeks, and distribution transformer lead times up to two years at sharply higher prices. National Infrastructure Advisory Council via CISA, and NREL, cited by Hade
- A single AI campus can request 300 to 500 megawatts at one node. Hade
- Announced behind-the-meter or co-located generation tied to data centers is on the order of 50-plus gigawatts, most identifiable equipment being natural gas. Cleanview, cited by Hade
- AI was roughly a quarter of data center workloads in 2025 and could be about half by 2030, with inference expected to overtake training as the dominant requirement around 2027. JLL, cited by Hade
- Dynamic line rating can raise line ratings by 10% to 40% in favourable conditions, and many grid-enhancing technologies can be installed within months without new rights-of-way. ESIG, cited by Hade
- In a modelled mid-sized utility, 400 megawatts of virtual power plant resource adequacy cost about $2m a year against about $43m for a portfolio of new gas plants and grid upgrades. Brattle via RMI, cited by Hade
- Buildings over 100,000 square feet were about 2% of roughly 5.9 million American commercial buildings in 2018 but about 34% of commercial floorspace and about 39% of commercial building energy use, which he works out to on the order of 118,000 large buildings. EIA’s 2018 commercial buildings survey, cited by Hade, the arithmetic his
- Engines from retired military aircraft could add up to 40,000 megawatts of theoretical generating capacity, which the agency itself warns is theoretical rather than a statement about feasibility. EIA, cited by Hade
07Where it’s contested
Nobody argues back, and the one place two voices meet is the introduction, where Lubershane recommends the essay rather than testing it.
- Hade, who wrote the argument, has a commercial stake in it. The introduction states that Energy Impact Partners invested in Hade’s company Brightfield, which was acquired by Voltus, an aggregator of distributed capacity, and Hade’s essay later offers a Voltus partnership as evidence the commercial model is arriving. The essay argues for the category his business sells into, and does not restate the connection in its own text.
- Hade’s own limits are explicit. Co-location will work in some places for some firms; grid-enhancing technologies buy time rather than substituting for new transmission; batteries are not magic; and no single bill or partnership solves the problem.
- The demand forecast is a wide range, and its authors make it conditional on hardware shipments, utilization and efficiency. The essay treats the growth itself as given.
- Two load-bearing sources cannot be checked. Several of the claims about what actually accelerates interconnection cite unpublished February 2026 memos.
- The assumptions it does not defend are that data center operators will accept enforceable curtailment, and that accreditation of aggregated portfolios can be made to work. He names accreditation as the hardest part and then proceeds as though it is settled.
- The concession is never sized. Granting that co-location will succeed for firms able to execute power-plant-grade projects, he never estimates how much of the announced pipeline that covers, which is what would decide whether it is a partial answer or a general one.