Field notes The Energy Transition for the Rest of Us

Catalyst N° 017 of 125 26 Feb 2024

Understanding the electric transformer shortage

with Tim Mills, CEO, ERMCO

In this note
  1. 01The question
  2. 02The answer
  3. 03The argument
  4. 04What you need to know first
  5. 05Details worth keeping
  6. 06Claims worth citing
  7. 07Where it’s contested

The question

Why did lead times for distribution transformers stay at one to two years long after the rest of the post-COVID supply chains cleared?

The answer

Because it was never mainly a COVID problem. Demand shifted structurally upward, ordering behavior amplified it, and manufacturing capacity had been roughly flat since 2007 and is slow and expensive to add. On top of that a proposed federal efficiency standard could force a switch to a different core material, which means a manufacturer deciding today whether to expand does not know what equipment to buy. Mills expects the single-phase pole-mounted shortage to clear soon and the pad-mounted and three-phase shortage to stay painful for another 12 to 24 months.

03The argument

Start with the puzzle. In 2018 a utility could send a purchase order for ten transformers or two hundred and have them in 12 to 14 weeks, and Mills says nobody worried about it. Today the single-phase pole-top units, the gray cans on utility poles, are normalizing but may still run beyond a year, and pad mounted units, single-phase and three-phase alike, run as long as two years. Every other COVID-era supply chain unkinked. This one did not, which means the COVID explanation was never the right one. Mills draws the distinction sharply: this was not the microchip problem, where carmakers physically could not obtain a necessary input. It was the toilet paper problem, a demand behavior problem. Because deliveries had been dependable for years, utilities did not forecast or pre-order. As lead times crept out, he thinks that kicked out more and more orders, which pushed the queue further out and confirmed the fear that caused it.

Behavior alone does not sustain a four-year shortage, though, and underneath it the demand curve genuinely bent. Mills went back through the history and found transformer volumes tracked the housing market closely, with the last comparable episode in 2006 and 2007 when US housing starts approached two million a year. Then housing crashed, transformer demand crashed with it, and manufacturers either left the business or moved resources elsewhere. His gut estimate is that total US capacity in 2021 was about what it had been in 2007. Meanwhile the demand side acquired drivers that did not exist 15 years earlier: federal infrastructure spending, electrification and EVs, renewables landing on the distribution system, and storm response, with natural disaster severity stepping up from 2017 onward, plus a housing market that was healthy if not at 2006 levels. Four or five variables arrived together against a manufacturing base sized for the previous era.

So why has supply not caught up by now, when everyone agrees the demand is real? Partly because the industry was already flat out. Mills describes plants running 24 hours a day, five days a week at 90 to 92% utilization, so the next incremental unit was the expensive one. Buying the weekend means hiring, and the plants sit in rural communities with little slack labor in a national market with very low unemployment, where staffing a new line means hundreds of people. A wholly new line costs on the order of a hundred million dollars, then waits on equipment lead times, so it is one to two years before production starts and longer before it ramps. And the core of the machine depends on a specialized input: grain-oriented electrical steel, which has exactly one US producer, Cleveland-Cliffs, already at full output. Foreign steel exists and competitors use it, at higher cost because of tariffs whose purpose Mills says he does not know.

Then the part that turns a hard problem into a frozen one. The Department of Energy has proposed a higher efficiency standard for distribution transformers. As initially written, Mills says it would make grain-oriented steel impractical and effectively require amorphous steel, which loses less energy when the transformer is sitting unloaded. Set aside that there is not enough amorphous steel in the world to build every transformer with it: 95 to 98% of American production currently runs on grain-oriented cores, and switching means new equipment, a changed process, a retrained workforce and, he expects, a drop in output before any learning curve arrives. That leaves the expansion decision undecidable. If he commits capital today, he does not know whether to buy grain-oriented or amorphous core equipment. An efficiency rule intended to save energy is, in the near term, a reason not to expand the very supply that is short. Mills expects a compromise rather than the original proposal, notes legislation from Senators Brown and Cruz that would hold current standards for a period, and thinks the question will be settled within one to three months.

04What you need to know first

Distribution transformer
The last-mile device that steps voltage down from the distribution network to what a house, factory or apartment building uses. Distinct from the large power transformers at generating plants and substations. It comes in three flavors: single-phase pole-top, single-phase pad-mounted, and three-phase, usually pad-mounted. The shortage is worst in the pad-mounted units.
The core
The electrical steel that surrounds the coil and does the voltage conversion. Its metallurgy sets both the transformer’s efficiency and what manufacturing equipment the plant needs.
No-load losses
Energy a transformer wastes simply by being energized, whether or not anything is drawing power through it. Amorphous steel is much better on this measure than grain-oriented steel, which is the entire basis for the proposed efficiency standard.

05Details worth keeping

  • Prices rose 75 to 100% on average over the preceding couple of years, then stabilized: roughly 5% in 2023 and a projected flat-to-5% in 2024. Mills attributes most of it to passing through commodity costs on electrical steel, oil, copper and aluminum, plus wage pressure.
  • Utilities recover that cost through rate cases, so it reaches consumers, and Mills says regulators are pushing back in places.
  • ERMCO completed an acquisition at the end of 2022 specifically because the acquired business had more headroom to expand output than the legacy company. Together they shipped about 85,000 more transformers in 2023 than in 2022, and Mills expects a similar increase in 2024.
  • The next technology step is power electronics rather than metallurgy. ERMCO’s GridBridge subsidiary has a low-voltage engine in testing in Europe. Mills puts it years out and more expensive for now.
  • The payoff he describes for that technology is voltage control: trimming output by 3 to 4%, still within specification for the connected load, across the whole grid at a peak moment would be equivalent to generating 3 to 4% more energy.
  • Mills’s closing view is that the shortage was foreseeable. If the country had looked honestly at the state of its infrastructure and at how fast energy policy was changing, he says, transformers and conductor were predictable pinch points.
  • Kann opens with figures for a different category than the episode covers: 100 or more weeks for some power transformers and up to 125 weeks for generator step-up units. Mills’s numbers are for distribution transformers.

06Claims worth citing

All figures as stated on 2024-02-26. Lead times, prices and the status of the federal efficiency rule were all moving at the time and should be treated as a snapshot rather than a current reading.

  • In 2018 distribution transformers arrived in 12 to 14 weeks, in quantities of 10, 100 or 200, and utilities were comfortable with the supply chain. Mills
  • Today single-phase pole-mounted units are normalizing but can still run past a year; pad-mounted single-phase and three-phase units run as long as two years. Mills
  • That is roughly four to five times the 2018 lead time in the better part of the market and eight to ten times in the worst part. This arithmetic is Kann’s, offered as a restatement, and Mills does not repeat or endorse the multiples. Kann
  • Up to 100-plus week lead times for some power transformers and up to 125 weeks for generator step-up transformers, described as “by some estimates.” Kann
  • US housing starts approached 2 million a year in 2006 and 2007, the last period when lead times ran this long. Mills
  • Total US transformer manufacturing capacity in 2021 was probably about what it was in 2007. Explicitly a gut estimate. Mills
  • Plants were running at 90 to 92% utilization, 24 hours a day, five days a week. Mills
  • A new production line takes one to two years before production starts, then more to ramp. On cost he begins to say hundreds of millions of dollars and corrects himself to a hundred million, so the figure is unclear as spoken. Mills
  • One US producer of grain-oriented electrical steel, Cleveland-Cliffs, running at 100% capacity; one US producer of amorphous steel. Mills
  • An estimated 95 to 98% of transformers made in America use grain-oriented steel. Stated as a guess. Mills
  • Prices up 75 to 100% on average, about 5% in 2023 and a projected flat to 5% in 2024. He dates the large increase only as “the last couple of years” and then describes 2023 and 2024 as the stable period, so exactly which years absorbed the 75 to 100% is not pinned down. Mills
  • About 85,000 additional transformers shipped in 2023 versus 2022 across ERMCO and its acquisition. Mills

07Where it’s contested

  • Whether manufacturers held back deliberately. Kann proposes a fool-me-once story, that memories of the 2008 housing crash kept the industry from expanding. Mills says it is more the former than the latter, but his own description is closer to paralysis than restraint: the orders were visibly outrunning production and nobody knew how to respond to a signal that might not hold for decades.
  • The efficiency standard’s outcome is unknown. Mills expects a compromise and does not think the original proposal will become the standard, but that is a prediction. His one-to-three-month timeline for resolution is also a prediction.
  • Several of his key numbers are flagged as estimates. The 2007-versus-2021 capacity comparison is a gut figure, the 95 to 98% grain-oriented share is a guess, and he says outright that he does not know why the steel tariffs were imposed.
  • The prognosis is a stance as much as an analysis. Mills twice says America rises to a challenge and predicts relief, citing capacity announcements over the prior 12 months. He gives no aggregate figure for how much capacity those announcements represent against the gap.
  • The vantage point is a manufacturer’s. Kann introduces Mills as someone both hurt by the crisis and, to some extent, benefiting from it, and Mills speaks throughout from a producer’s side of the transaction. The demand-side account, particularly the claim that utilities over-ordered out of panic, is not tested against a utility voice in this episode.

Cite as: “Understanding the electric transformer shortage,” The Energy Transition for the Rest of Us, note on Catalyst with Shayle Kann, February 26, 2024. CC BY 4.0. View the Markdown