Field notes The Energy Transition for the Rest of Us

Catalyst N° 062 of 125 8 May 2025

The US nuclear groundswell

with Chris Colbert, co-founder and CEO, Elementl Power

In this note
  1. 01The question
  2. 02The answer
  3. 03The argument
  4. 04What you need to know first
  5. 05Details worth keeping
  6. 06Claims worth citing
  7. 07Where it’s contested

The question

The US nuclear market is clearly stirring again. Does a groundswell like this one turn into an actual wave, or into another 2007-style mirage?

The answer

Colbert argues this one is different, and the reason is entirely on the demand side: hyperscalers who want clean baseload, have enormous balance sheets, and have finally agreed to fund development spending rather than only sign a power purchase agreement. But nothing is settled. No reactor vendor has crossed the commercial readiness line yet, and the cost case depends on repeating a design enough times to climb the learning curve, which has not started.

03The argument

Kann picks the word groundswell deliberately, because a groundswell sometimes becomes a wave and sometimes does not, and the United States has completed exactly one new nuclear project in decades. Colbert, who was recruited into the 2007 renaissance and watched it fail, locates the difference in what broke last time. Then, regulated utilities were being asked to underwrite $17 billion to $20 billion projects against market capitalizations of $20 billion to $30 billion, on the twin expectations that demand would grow and gas would stay expensive. Neither happened. Today gas prices are near all-time lows, which by the old logic should be fatal, and yet demand is there anyway, because hyperscalers want reliable, clean baseload contracted for a long time.

The load-bearing change is not the offtake contract itself. Nuclear development costs hundreds of millions of dollars before a final investment decision, against tens of millions for renewables, and no power purchase agreement funds that. What took a year and a half to sink in with the hyperscalers, on Colbert’s account, is that they had to put money into development, not just into technology, and the Google deal is his example of that money arriving at the front of the process. That reframes the entire business. Elementl inverts the renewables development sequence: find the customer first, then the site, then work with the utility the customer already knows, then choose the technology last. An early site permit is technology-agnostic, so the site can be proven up while the vendor field sorts itself out, and only the later construction permit is design-specific.

Which is convenient, because Colbert’s honest position on vendors is that nobody has arrived. Billions have gone into both Generation III lightwater designs and Generation IV designs such as high-temperature gas and sodium-cooled reactors, and all are near the end of development while each still solves for something, whether supply chain, licensing or cost estimation. He cannot say which will succeed and says so plainly, betting only that three or four at minimum will. He does separate technology risk from execution risk sharply: lightwater is 50 to 60 year old technology, the Navy has run it since the fifties, and the EPR, APR1400 and AP1000 all struggled to the finish line and then worked. So for lightwater there is, in his framing, no technology risk left, and the challenge is entirely in de-risking the front end and executing in the field.

On cost his thesis is repeatability, and his analogy is assembling four identical pieces of IKEA furniture, where the first one breaks and the fourth is quick. He points to Vogtle unit four coming in roughly 40% below unit three. This is why the Google deal is three projects rather than one, and why the reactor size lands between 75 and 300 electric megawatts rather than gigawatt scale: you cannot write a check big enough to order enough large reactors to get repetitions, so smaller units buy more swings at the bat. Underneath sits the unglamorous second level, meaning a finished design, a supply chain lined up and above all a labor plan. Labor is the input he calls most uncontrollable, since crews can walk to the data center project down the road, and his answer is to pay the premium rather than eat the delay. One siting inversion is worth carrying too. Colbert expects it to be easier to permit and build a nuclear plant than a new transmission line, everywhere he has worked, because transmission crosses people’s property without leaving economic benefit behind. So sites go where transmission already exists, meaning former coal plants and large industrial sites, and finding sites is not the hard part. The customer decides where, and hyperscalers choose more by which utility they trust than by geography.

04What you need to know first

Offtake
The contract to buy the power, historically a power purchase agreement signed once the plant is close to real. That is exactly what Colbert says is no longer sufficient for nuclear.
Final investment decision
The point where a project commits the capital to build. Everything spent before it is development capital at risk, and who carries that risk is the central question here.
Design certification, construction permit, operating license
The three rungs of the US nuclear regulatory ladder. Several designs hold certification, some developers have or are seeking construction permits, and nobody has an operating license for a new design, which is the rung that lets you load fuel.
Lightwater and non-lightwater
Lightwater reactors are the conventional water-cooled designs in use since the fifties. Non-lightwater covers Generation IV approaches such as high-temperature gas and sodium cooling, with better safety characteristics and less mature fuel and supply chains.

05Details worth keeping

  • The utility risk math is the cleanest thing in the episode. Fossil plant development expects two to three times return on capital at risk before the investment decision; regulated utilities are capped near 10%. Three times the risk for a 10% return does not work, which is the structural reason a third-party developer exists at all.
  • The corresponding utility appetite is for finished assets. Colbert says utilities would happily pick up an operating or largely de-risked plant, and uses Constellation’s share price since it floated as evidence for what the market pays for nuclear in a fleet. Constellation is a merchant generator, not a regulated utility.
  • Elementl’s own schedule as described: site work through 2025 and 2026, construction permit 2026 to 2028, construction starting 2029, operating by 2032 or 2033.
  • Site criteria are narrower than the geography suggests: roughly 100 acres or less for a small modular reactor, seismic qualification matched to the design, and access to existing transmission.
  • He splits the decade by technology: small lightwater reactors commercially in the early 2030s, non-lightwater designs in the late 2030s.
  • The benchmark he wants is a combined cycle gas plant, roughly two years of development and licensing plus two years of construction. Nuclear at five or six years total would, in his words, make it a real equal discussion.
  • His near-term North American marker is Ontario Power Generation’s BWRX-300, about to start nuclear safety-related construction and to be operational around 2029 or 2030.

06Claims worth citing

All figures as stated on 2025-05-08, attributed to the speaker and not verified independently. Costs and schedules for plants that do not exist yet are targets.

  • The Google deal covers three projects totaling at least 1.8 gigawatts, at least 600 megawatts each. Kann and Colbert
  • The size sweet spot is roughly 75 to 300 electric megawatts. Colbert
  • Around $10,000 per kilowatt once down the learning curve, so about $6 billion for a 600 megawatt plant, with the first unit perhaps 15% to 20% above that. Colbert
  • Vogtle unit four came in about 40% below unit three, stated with an “I think.” Colbert
  • Nuclear Regulatory Commission reviews that once took four years now take two, with a hope of getting to a year or a year and a half. Colbert
  • Total development-to-operation of seven to eight years today, with a path he sees to five or six. Colbert
  • First-renaissance projects of $17 billion to $20 billion against utility market capitalizations of $20 billion to $30 billion. Colbert
  • Nuclear development capital runs to hundreds of millions of dollars, against tens of millions for renewables. Colbert
  • Elementl’s stated goals: some quantity under construction by 2030, 10 gigawatts by 2035 and 100 gigawatts by 2040, now tracking 4.2 gigawatts by 2030. The 2030 figure is garbled in the transcript; his follow-on that 4.2 gigawatts has “quadrupled” it suggests the original was 1 gigawatt, but check the audio before quoting. Colbert
  • He expects at least three or four reactor vendors to get through development successfully, without naming them. Colbert
  • A roughly $5 per hour wage premium is worth paying to hold a construction crew, because the cost of delay is about five times that. Colbert

07Where it’s contested

  • The premise is left open by the host. Kann’s framing is that a groundswell may or may not become a wave, and he says the operative question is which way this goes. He also discloses that EIP is not a neutral party here, having helped create Elementl and taken a board seat.
  • ”Different this time” comes from a participant in the last time. Colbert was recruited into the 2007 renaissance and concedes Vogtle, its one surviving product, had issues. His case rests on demand-side conditions that are real now and could change.
  • Vendor readiness is the load-bearing assumption and it is unresolved. He says the technologies are almost there, that he cannot tell which will succeed, and that he is comfortable three or four will. That is a judgment call rather than an analysis he shows, and the technology-agnostic strategy rests on it.
  • The cost numbers do not obviously reconcile. A 15% to 20% first-unit premium over a settled $10,000 per kilowatt sits awkwardly beside his own example of Vogtle unit four landing 40% below unit three. The two are measured against different baselines, a repeat unit on one site versus a settled cost down a multi-project curve, and he does not connect them.
  • Labor is described two ways in the same breath. He calls it the most uncontrollable aspect of nuclear construction and then says solving it is “not that hard” if you pay properly and treat people well.
  • Regulatory improvement is asserted from personal observation. The four years to two years figure comes from what he has seen over 15 years, and he says plainly that the timelines he wants are not here yet.
  • No technology risk is a claim about the reactor only. He limits it to lightwater designs and immediately says the challenges have traditionally been in construction and project execution, a different and unretired risk.

Cite as: “The US nuclear groundswell,” The Energy Transition for the Rest of Us, note on Catalyst with Shayle Kann, May 8, 2025. CC BY 4.0. View the Markdown