Catalyst N° 128 of 133 1 Oct 2026
ERCOT batteries: Boom, bust, or rebound?
with Brandt Vermillion, US market lead, Modo Energy
In this note
The question
Texas built a huge fleet of grid batteries and the money dried up. Will data center load growth bring the profits back, and when?
The answer
Vermillion expects a recovery but not soon. Modo’s own model shows price volatility returning in a big way around 2029 to 2030, enough to clear the roughly $100 per kilowatt that a new battery needs for at least a couple of years. It could come sooner if load arrives fast and coincides with extreme weather, and he stresses that nobody has enough information on demand growth to know the timing. Until then, today’s fleet earns well below what it needs.
03The argument
The collapse is mostly self-inflicted. Texas batteries first made their money from ancillary services: payments for standing ready to steady the grid’s frequency or cover a sudden loss of supply. In 2022 and 2023 those services supplied most of a battery’s revenue. But the grid operator only buys so much of them, and once installed battery capacity outgrew that amount, batteries moved into energy arbitrage, charging when power is cheap and selling when it is expensive. That market is far deeper, since Texas serves 60 to 80 gigawatts of load at peak, but the same mechanism followed them there. The more batteries compete to be dispatched in the high-price hours, the lower they have to offer, and the more they suppress the volatility they earn from. Vermillion calls this cannibalization. Revenue fell from nearly $200 per installed kilowatt in 2023, a hot summer when ancillary services were not yet saturated, to around $30 over the last 12 months. That is well below what a new two-hour system needs to be financed.
Kann raises the obvious confounder: Texas price spikes come from weather, and mild weather alone suppresses them. Vermillion grants weather a real role but places it second. The majority of the decline comes from how much battery capacity was built, with weather as a compounding layer on top. He is careful that recent summers were not cool, just not extreme. Extreme weather can still produce spikes, and his account of Storm Fern in January shows that the fleet’s own behavior now shapes them. When forecasts missed and overnight real-time prices stayed high, many operators hesitated to recharge, so the next morning only about a third of the fleet’s capacity was charged and prices reached four figures. How much charge the fleet is holding has become a key variable in its own right.
Against that sits the case for building anyway, which Vermillion lays out as the developer’s thesis. Power markets are cyclical, infrastructure responds with a lag, and low prices cure low prices. What is unusual this time is the scale and speed of the demand that wants to connect, mainly data centers. The headline requests are very obviously inflated, but even a tenth of them would be transformational for a grid that peaks at 91 gigawatts. Meanwhile he sees the first signs of supply slowing, at least for the next year or two: the battery queue has stopped growing, new installations are no longer doubling each year, projects are withdrawing even after signing interconnection agreements, and a merchant gas plant would face the same weak prices a battery does. So demand could quickly outrun what is today an oversupplied system. The catch is the gap. Even a developer convinced that volatility returns in 2028 has to survive the lean years first, and a third-party lender wants a contract that covers debt service in the meantime, such as a toll, a revenue share or floor, or a swap. Buyers and sellers of those contracts are far apart on price and length.
Kann pushes on the strongest objection to the recovery story. If new data centers bring their own on-site generation, they could run it exactly when prices spike, adding load without adding to the peak that batteries are waiting for. Vermillion takes it seriously and builds it into the model, but argues the timing works against it in the near term. Data centers arriving in the next one to three years may already have secured grid connections because the system is oversupplied, so they are probably going to lean less on their own generation. Later, as the system tightens, more will be offered partial connections and will bring their own power. His rough rule of thumb, which he describes as substantially guesswork, is that 50% to 70% of nameplate data center load ends up drawing from the grid in the long run.
04What you need to know first
- ERCOT
- The episode uses the name for both Texas’s grid operator and the electricity market it runs, without spelling out the letters. Kann calls it “more or less” an energy-only market: there are no capacity payments to lean on, so resources earn mainly from the electricity they sell.
- Merchant
- A project that sells into the market at whatever prices it finds, with no long-term contract fixing its revenue.
- Ancillary services versus energy arbitrage
- The first is paid standby work keeping the grid stable, a lucrative but shallow market. The second is buying low and selling high on power prices, a deeper market whose returns depend on how volatile prices are.
- Duration
- How many hours a battery can discharge at full power. Longer batteries can ride out a price spike that outlasts the first hour.
05Details worth keeping
- Duration in Texas has been lengthening. Batteries were almost all one-hour at first because ancillary services set no real duration rules. New rules on how much energy must back each megawatt of service, cheaper cells and the shift to arbitrage pushed the average toward two hours, with some 2.5 to 3 hour and a couple of 4-hour projects now arriving. California’s batteries are mostly four hours or more because of how its capacity rules are built.
- Some of this summer’s high-price days came in two waves. Batteries discharged into the forecast peak hour, ran low, and then a second real-time spike an hour or two later, driven by a combination of things such as the wind and load forecasts, rewarded batteries that held charge back or were simply longer.
- Flatter round-the-clock loads are making the evening handoff off 30 to 40 gigawatts of solar harder for the grid operator, which contributes to these spikes.
- Mergers and asset sales are happening, but less than the economics would suggest. Older projects earned solid returns from early ancillary services, or at least passable 2024 revenue that kept them above debt service, and many owners are large, well-capitalized power companies or utilities that may be able to weather the storm, perhaps having self-financed.
- Tolling deals have been a useful tool but are not the predominant form of contract. Any such hedge will scale down the developer’s upside quite a bit, especially at a relatively low strike price; that is the trade-off accepted for financing.
- Vermillion expects the same arc in other markets. Batteries always go to ancillary services first, saturate them, and move on. PJM, another US grid market that the episode does not further describe, redesigned its regulation market last year and prices have been extremely high, with paybacks in a single year, but that market is shallow and should compress once batteries there reach one to two gigawatts. For a low-growth market like California, he asks whether recovery would instead come from thermal plant retirements changing the price shape.
- Kann adds that ancillary-service saturation is a recurring story in batteries, citing PJM as where the first grid-scale batteries went.
06Claims worth citing
All figures as stated on 2026-10-01. Fleet size, queue and revenue figures in this market move quickly.
- Texas had about 200 megawatts of grid-scale batteries at the start of the decade and 16.5 gigawatts, nearly 29 gigawatt-hours, by the end of June 2026. Kann
- Vermillion gives the fleet several ways within the episode: 17 to 18 gigawatts fully approved for commercial operation and over 20 gigawatts having completed construction early on, then 18 to 19 gigawatts commercially operational “today” from a start-of-year base of about 14 gigawatts, with 5 to 6 gigawatts of additions expected by year end. The figures do not fully reconcile, so check the transcript before quoting one. Vermillion
- About 5 to 6 gigawatts were added in 2025. Vermillion; Kann puts it at 6 gigawatts
- The average Texas battery earned roughly 84% less in 2025 than in 2023. In 2023 there were 58 days on which it earned at least 50 cents per kilowatt; in 2025 there were three. Kann
- A two-hour battery in Texas needs roughly $100 per installed kilowatt, maybe a little less, to be financeable. He gives it as the rule of thumb Modo has heard and calls it a shifting target as costs move. Vermillion
- In 2022 to 2023 most batteries earned more than 90% of their revenue from ancillary services (later in the same answer, 80% to 90% in 2023); today close to 80% comes from energy arbitrage. Vermillion
- The battery interconnection queue has stalled at 150 to 160 gigawatts after growing by dozens of gigawatts a year. Vermillion
- Something like 13 to 15 gigawatts of project capacity withdrew after signing interconnection agreements, once a near guarantee of being built; he introduces it as something Modo “tracked last year,” which leaves unclear whether the withdrawals or the tracking fell last year. (Vermillion) Kann’s monologue gives a record 13.7 gigawatts withdrawn in the first half of this year and says new queue entries have halved from their peak. The two may be the same figure stated loosely; they are not reconciled on air.
- Projects wanting to connect, primarily data centers, total 400 to 500 gigawatts (rendered “4 or 500”), a figure he calls very obviously inflated. He expects connection to stretch over five to six years. Vermillion
- Overnight before the critical morning of the January storm, real-time prices ran around $150 against $50 day-ahead. Vermillion
- More than 20 gigawatts of aging coal and gas in Texas is losing money, and some will shut. Kann
- PJM’s regulation market is about 600 to 700 megawatts deep, against about 500 megawatts of batteries there today. Vermillion
07Where it’s contested
- The timing is explicitly uncertain. Vermillion says there is not enough information on demand growth to know how fast it arrives, and that his model date could be pulled earlier by fast connections combined with a severe summer or winter. Both speakers mention ERCOT’s “Batch Zero” process, which the episode does not explain; Kann says it may delay some data centers, and Vermillion ties faster demand growth to its being finalized next year. Kann says outright he has no idea when recovery comes.
- The monologue’s macro case is Kann’s. The money-losing coal and gas, sold-out gas turbines and batteries as the resource that can show up on time are stated by Kann; Vermillion’s case rests on load growth outpacing slowing supply.
- ”Collapsed” is hedged. Vermillion calls it a strong word before conceding that is roughly what happened to revenue.
- Weather versus overbuild. Kann frames the weather question as hard to untangle; Vermillion assigns the majority to overbuild without putting a number on the split.
- On-site generation could blunt the recovery. Raised by Kann as “one maybe big risk.” Vermillion’s answer depends on a near-term versus long-term timing argument and a grid-draw ratio he describes as largely guesstimated.
- What went unexamined. The $100 hurdle rests on costs Vermillion calls a shifting target. His model accounts for the queue, but the episode does not quantify whether batteries still being added this year push recovery past the model’s date, a tension Kann names in the monologue.