Can geothermal power get cheap the way shale oil and gas did, and what would it take to build it far beyond Utah and Nevada?

The answer

Jewett’s answer is that key pieces of the shale playbook were easy to adopt, chiefly one design repeated well after well and land leased before anyone wanted it, and that Fervo has kept to off-the-shelf oilfield tools below ground. Money is the hard part, and she thinks it still is, because a company can typically finance only what it has already proven rather than what it expects. She expects the $3,000-a-kilowatt goal to arrive through many small improvements rather than one breakthrough, ties reach beyond Utah and Nevada to that falling cost, and asks of permitting that it be predictable enough for risk retired in one state to count in the next.

03The argument

Jewett’s framing line is that Fervo runs the shale playbook twenty years later with the answer key, and the lesson she takes from shale is specific. In every basin an operator’s first wells are its most expensive, and costs fall as it learns the resource, spreads fixed infrastructure over more activity, and eventually fights over minutes of nonproductive time. So Fervo built wellfield plans to drill the same well over and over without redesign, and carried the idea to the surface with near-identical power plants, each learning from the last. She calls these pieces of the shale strategy very easy to adopt. Below ground the supply chain is close to oil and gas, differing mainly in higher temperatures and often wider diameters, and Fervo has held to off-the-shelf tools rather than inventing its own, which is why its development temperatures have risen only as fast as existing equipment is rated for, with suppliers upsizing tools and switching materials as they came to believe in the company. The land strategy followed the same logic: on the conviction that the physics would eventually work, the founding team leased the best geothermal acreage that also had a believable route to a customer, while nobody else cared about it.

The intuitive story is that a pilot proves the concept and then drives the cost curve, and when the host puts that premise to her, Jewett gently reframes it. Fervo moved through deliberately escalating steps: desktop modeling, a stimulation on an existing well, then its own well system, Project Red, which showed that heat could be flowed and extracted. Fervo insisted Red be a commercial pilot as well as a technical one, with a buyer (Google), because doing the two in sequence would have been too many steps. But Red was a minimum viable product, built to learn from and then repeat at scale rather than being “really repeatable” in its own design, with only two wells alike. There were large gains from its first well to its second, yet the learning curve only really showed itself from the third well onward at Cape Station, the large greenfield development Red green-lit. The curve needs volume, and in a business she calls capital-intensive, volume needs money.

That is the turn in her account: financing has been the hardest thing for Fervo, and she thinks it remains so. You skate to where the puck is going, but you can typically finance only where you have got to. At the front of a technology cycle the cost of capital stays high however creative you are, because there is no operating record, the technology is not yet proven to work, and, at Red, there was no full-scale fifteen-year power purchase agreement with a creditworthy buyer. The way down is to announce milestones and expected results in advance, come back with results that match, and let each data point widen the financing available; she calls this financing 101, applying in spades to a technology perceived as high-risk. Two outside factors helped, arriving at the same moment: the Inflation Reduction Act tax credit, which she calls incredibly helpful, and rising demand and willingness to pay for geothermal in 2023 and 2024. Together, she says, they convinced people the projects would be financially healthy, and she thinks that helped attract more traditional financing.

Demand and geography close the argument. Jewett rejects the idea that the business is alive only because of hyperscalers. She joined convinced of a large market before AI was on her radar, driven by rolling blackouts, renewable portfolio standard targets and the retirement of nuclear and older fossil plants, even without meaningful load growth. AI added to that demand in a meaningful way and made it more obvious; on her account it did not create it. Geographic reach, which she calls the reason Fervo exists, she ties to cost: geothermal could be a global resource because its cost is coming down enough to compete in many places. What she wants from permitting reform is predictability, so that risk pulled out through repeated proof points in Utah carries into Nevada, New Mexico or Colorado instead of resetting the risk profile and the financing playbook in each new state, which would undo the track record her financing argument depends on. Nor does she expect one breakthrough to reach the cost goal: it will come little by little, from small, human-led improvements, an answer she concedes disappoints people asking for the big unlock.

04What you need to know first

Enhanced geothermal
Conventional geothermal depends on hot water or steam already trapped in the rock. Enhanced geothermal creates the reservoir by fracturing hot, dry rock and circulating water through it. That description comes from the host’s monologue; Jewett says only that Fervo’s wells were drilled and fractured so heat could be flowed and extracted.
Learning curve
The fall in cost that comes from repeating the same job: each identical well or plant gets cheaper as the operator learns the ground, shares fixed equipment and cuts idle time.
Power purchase agreement, or offtake
A contract in which a buyer commits to purchase a project’s output. Jewett contrasts the “creative” offtake signed for the pilot with the full-scale, long-term kind that persuades financiers.
Cost per kilowatt
A cost measured against generating capacity, not against electricity delivered.

05Details worth keeping

  • Jewett first tried oil and gas as a final college internship, to understand “the dark side of energy,” then joined a traveling Schlumberger fracturing crew out of Rock Springs, Wyoming. After an MBA she returned to oilfield services before finding subsurface clean-energy companies.
  • Project Red’s build: after a four-stage stimulation on an existing, highly deviated well, a planned two-well system at the same site ended up as three wells, two horizontal and one vertical for monitoring.
  • Cape Station on the ground: rows of multi-well pads, power plants built to look alike, and a transmission line with Fervo’s own substation to the grid. She calls multi-well pads a Fervo first in geothermal, replacing the single vertical well per pad used before. A data center, by contrast, she describes as a series of HVAC-equipped warehouses.
  • Fervo expects to deliver power three ways: existing transmission, new transmission, and direct connection to a customer’s load behind the meter. She welcomes the bipartisan Senate proposal for more predictable in-state and interstate transmission, and names a bill the transcript renders as “BAAJA,” not spelled out, as the kind of measure that would make federal permitting consistent across states.
  • On geothermal’s bipartisan appeal she declines the credit: the story sells itself, as a shale-adjacent technology that redeploys the shale workforce, tools and innovation and replaces fossil fuel one for one.
  • In 2023 she expected Fervo to be selling to Google in a meaningful way by 2026, but did not “necessarily” expect to be talking about a specific potential co-located development as the buyer.
  • Being public has not changed the day-to-day. The cost is constant market feedback that, it feels to her, does not always track operational milestones; beyond the capital raised, the benefit is a much larger audience learning about geothermal.

06Claims worth citing

All figures as stated in an episode published 2026-11-10. Jewett says the first commercial plant came online “last month”; the host’s monologue says operations began in September. The transcript gives no recording date. Capacity, cost and financing figures for a young developer move quickly.

  • Fervo’s first commercial-scale power plant, 33 megawatts in southwest Utah, came online “last month,” the first of what she says will be many at Cape Station. Jewett
  • A visitor to Cape Station today sees three “fully baked” power facilities and others under construction. Alongside her statement that the first plant came online last month, she does not say how many of the three are generating. Jewett
  • Cape Station is slated to deliver roughly 500 megawatts at full capacity in 2028. Jewett gives no target capacity. Johnson, monologue
  • Cape Station pads carry eight to 10 wellheads each, three pads in a row. Jewett
  • Development temperatures went from 375°F early on to 400°F and are now higher, tracking the top rated temperature of existing tools. Jewett
  • The geothermal tax credit went from reliably 10%, year after year, to 30%, 40% or 50% with adders. Jewett
  • Geothermal demand, willingness to pay and power purchase agreement prices all rose in 2023 and 2024. No prices are given. Jewett
  • Electricity load had not grown at any meaningful rate for 20 years before AI. Jewett
  • The goal is $3,000 a kilowatt for enhanced geothermal “at scale,” with no date attached. Jewett
  • Fervo “IPO’d for $2.2 billion” in May, in her words, presented as capital to deploy. The host separately puts the IPO valuation above $7 billion. Jewett; valuation, Johnson
  • Fervo leased hundreds of thousands of acres in the West at “something like” $4 an acre on average, a story Johnson says he heard from Tim Latimer. Johnson adds that he thinks some of that acreage now trades at hundreds of dollars. Jewett describes the strategy but does not confirm the figures. Johnson, relaying Latimer; the current price is Johnson’s own
  • Fervo’s public filings describe an opportunity of “something like” 300 gigawatts of US geothermal over time. Jewett does not repeat the figure. Johnson, citing Fervo’s filings
  • Fervo is the only enhanced geothermal company to have delivered at utility scale; Project Red was a 2023 pilot in Nevada; Tim Latimer started the company in 2017; Google, Southern California Edison and Shell have signed power purchase agreements; two more projects are in the works. Jewett confirms only Google, as Red’s buyer, and 2017 as the year leasing began. Johnson
  • The shale revolution brought down US emissions by replacing coal with gas, and geothermal will do the same by replacing gas. Jewett

07Where it’s contested

The host challenges nothing, but the guest quietly departs from his framing in several places, and those divergences are the main content here.

  • AI is not the premise. The introduction says Fervo has diversified its customers beyond the AI boom. Jewett’s order is the reverse: she calls hyperscaler dependence a misconception and says the demand case came first.
  • Project Red was not the cost-curve step. The host’s question presumes it was; her reframing is in the argument above.
  • No one places a data center at Cape. Asked to picture a large geothermal project near an AI data center, she sketches a data center only generically and describes Cape Station’s pads, plants and grid connection. The host’s recap joins the two sketches into one scene. Neither says a data center sits at Cape, and she calls co-location a “potential” development.
  • Transmission. The host frames the problem as getting lines to Fervo’s public land, and the Senate proposal as easing transmission on public lands. Jewett says existing transmission was always the plan and values the proposal for predictability; she does not mention public lands.
  • The central claim is unquantified. The learning curve is the episode’s spine, yet no per-well cost, drilling time, current cost per kilowatt or electricity price appears, so the $3,000 goal has no baseline. That drilling times and costs have plummeted is the monologue’s claim, not hers.
  • Her own hedges. Geothermal “could” be a global resource, and cutting enough cost would make it “potentially” the cheapest electricity on Earth; she says the ambition feels crazy and happily accepts being called “the crazy geothermal lady.”
  • A question nobody asked. The host remarks in passing that federal tax law has been changing a lot, then asks why geothermal has stayed above the political fray. No one asks whether geothermal’s own credit has changed, so the episode’s financing story rests on the credit as she describes it.
  • The guest’s stake. Jewett is an executive of the newly public company whose plan the episode describes. Its forward figures, from the cost goal to the many plants planned at Cape, are company targets rather than results.

Cite as: “How fracking paved the way for epic geothermal growth,” The Energy Transition for the Rest of Us, note on Critical Capital, November 10, 2026. CC BY 4.0. View the Markdown