Catalyst N° 002 of 125 8 Dec 2022
Solving the conundrum of industrial heat
with John O’Donnell, co-founder and CEO, Rondo Energy
In this note
The question
Industrial heat is about a quarter of global emissions, factories need it around the clock, and energy can be more than half their cost of production. How do you decarbonize it?
The answer
Not by inventing a new way to make heat. Electricity already makes heat at almost any temperature industry uses, and nothing technical stops a factory from plugging in today; the obstacle is that cheap electricity is only cheap for part of the day while the factory runs continuously. So O’Donnell’s answer is to buy power in the cheapest hours, store it as heat and release it steadily, which loses very little because the energy never goes back to electricity, and which he argues needs only about 20 hours of storage. Which option is cheapest still depends on the local power market and the temperature the process needs.
03The argument
Start with how large and how varied the category is. O’Donnell puts heating and cooling at about half of world final energy use, heat at about 95% of that, and industrial heat alone at roughly a quarter of world energy use and a little more than a quarter of world carbon dioxide emissions, because more than about 80% of heat comes from burning coal, oil or gas. But it is not one thing. Pasteurizing milk wants about 80 degrees Celsius, refining about 200, and cement runs two thirds of its energy near 1,100 degrees and the rest near 1,800, which he calls the highest temperature in use anywhere. Roughly 80% of industrial heat sits below about 350 degrees. Under about 600 degrees the heat usually travels around a plant as steam from a boiler; above that it is often flame in direct contact with the product, as in a rotary cement kiln. And every substitute has to pass a cost test first, because these are commodity businesses where energy can be 40% to 60% of the cost of production.
That test sorts the options quickly. Biogas drops straight into existing equipment with no plant changes, but supply is very limited and it trades at roughly four times the price of natural gas. Hydrogen needs only modest burner and boiler modifications and reaches the highest temperatures, but it takes about two units of electricity to deliver one unit of heat, and O’Donnell is emphatic that this ratio is set by physics and will not improve even as electrolyzers get cheaper. Heat pumps invert that arithmetic, turning one unit of electricity into three units of heat, but only up to about 110 degrees, and they have to run all the time rather than only when power is cheap. Direct electric resistance heating and electric arc furnaces are mature and cheap to install, and operators already pair electric and gas boilers and switch between them on price. The limit there is the calendar: in the United States he sees at most about 30% of the hours in a year with clean power and perhaps 40% with low-cost power, so running on live electricity is interesting at the margin but will not get a plant a 90% or 95% emissions cut unless it sits somewhere like northern Quebec with abundant hydropower.
The reason that ceiling matters is the constraint every option has to satisfy. Large industrial processes run essentially continuously, roughly 8,700 hours a year with one annual shutdown for inspection, because restarting a smelter or a refinery can take weeks. Kann frames this as a purely economic problem; O’Donnell half agrees and half corrects him, saying it is economic and also somewhat technical, precisely because of that ceiling on cheap hours. So the move is to decouple buying electricity from using heat: charge a thermal store when power is cheap or curtailed, then deliver heat steadily. The class is above about 95% efficient from electricity in to heat out, and Kann draws the contrast that makes this surprising: very few batteries reach 95%, but here nothing converts heat back into electricity, which is where the losses normally live. Three costs decide which design wins: how fast it can charge, because the hours of near-zero prices are much shorter than the generating day, maybe four hours of curtailment inside an eight-hour solar day; what the core costs, where O’Donnell’s line is that the box costs a lot more than the rocks; and what it costs to convert stored heat into whatever the process wants. Rondo stores heat in brick, which blast furnaces have done since 1828, and claims a faster way of heating it; others use gravel or sand, molten nitrate salts, melting metals or superheated graphite.
Two conclusions follow. First, despite the long-duration storage framing, O’Donnell sees no business case beyond about 20 hours, because the fallback when renewables are absent is burning fuel in a boiler at about 90% efficiency rather than in a power station at about 50%. At 20 hours of storage, something else supplies roughly 10% to 12% of annual energy, fuel now and hydrogen later, and that is cheap enough to accept. Second, the binding constraint becomes access to cheap clean power at the scale of tens to hundreds of megawatts, which in 2022 means fighting permitting and multi-year interconnection queues, and he argues that some of the resulting price gap is rent extraction by projects already connected. Kann puts a thesis to him: falling renewable costs against rising delivered grid costs should eventually produce industrial grid defection and a migration of heavy industry toward the wind corridor and the solar South. O’Donnell takes half of it. He agrees about the migration, and Rondo builds off-grid projects today because a small company is impatient, but he does not accept defection. For the next 20 years the work is repowering plants where they already stand, and his expectation is that heat batteries become valuable to the grid rather than absent from it: a dispatchable load where the utility is asked not for 250 megawatts of firm service but for 8,000 megawatt-hours today, delivered on whatever schedule suits the system.
04What you need to know first
- Process heat
- About three quarters of the energy used to make physical goods is heat, not electricity. It arrives indirectly, usually as steam, or directly, with combustion touching the product itself.
- Curtailment
- Hours when wind or solar output exceeds what the grid can take and prices fall to zero or below. These hours are the cheap input the approach runs on, and they are shorter than the generating day.
- Thermal energy storage
- Electricity becomes resistance heat, the heat sits in a solid or liquid medium, and it comes out later as heat. The round trip stays above 95% only because the energy never goes back to electricity.
- Dispatchable load
- A customer whose consumption the grid operator can schedule, the mirror image of a dispatchable power plant.
05Details worth keeping
- A typical cement plant might draw 55 megawatts of electricity and 1,000 megawatts of heat, which is why decarbonizing industry is mostly a heat problem, not a power problem.
- Which fossil fuel a plant burns is mostly an accident of local availability and scale, not a requirement of the process. Coal survives where equipment is large; gas displaced coal and oil worldwide over the past 20 years.
- The efficiency argument extends to combined heat and power, where a boiler drives a turbine and the waste heat runs the process. Swap the boiler for thermal storage and the system still delivers about 95% of its input as heat plus power; making electricity alone from stored heat drops to roughly 45% or less.
- The 24/7 rule has exceptions at the small end: cheese factories and dairies may run five days a week, which changes their economics.
- O’Donnell expects the Inflation Reduction Act to spread negative power prices well beyond places like Oklahoma, partly because the production tax credit rewards generating into them.
- Moving power long distances is not the physical barrier people assume: high voltage direct current carries it 1,000 miles for about 4% loss. The harder problem he names: wires built for coal plants at 100% capacity factor now serve wind farms at 40%, so the same wire earns less.
06Claims worth citing
All figures as stated on 2022-12-08 and attributed to the speaker rather than verified. Prices, interconnection times and deployment rates from this period should be treated as historical.
- Industrial heat is roughly 25% of world energy use and a little more than 25% of world carbon dioxide emissions; more than about 80% of heat comes from coal, oil or gas. O’Donnell
- Industrial heat is the single largest source of greenhouse gas emissions globally, larger than all transportation combined. The host’s framing; the guest states the compatible but differently worded share above. Kann
- 99 exajoules of industrial heat in 2019, needing about 10,600 gigawatts of wind and solar at typical capacity factors to replace. O’Donnell
- About 80% of industrial heat is below about 350 degrees Celsius; cement runs two thirds of its energy near 1,100 degrees and one third near 1,800, the highest in commercial use. O’Donnell
- Energy can be 40% to 60% of the cost of production in commodity industries. O’Donnell
- Biogas trades at about a four times price premium to natural gas, with very limited supply. O’Donnell
- Hydrogen takes about 2 units of electricity per unit of heat, a ratio fixed by physics; heat pumps give about 3 units of heat per unit of electricity but only up to about 110 degrees Celsius; electric thermal storage takes about 1.1 units of electricity per unit of heat and reaches about 1,500 degrees, covering all but roughly 5% of industrial heat. O’Donnell
- Live direct electrification gets at most about 30% of annual hours at clean power and perhaps 40% at low-cost power in the United States. O’Donnell
- The whole class of electric thermal storage is above about 95% efficient from electricity to delivered heat. Stated as a property of the class, with no third-party data. O’Donnell
- No business case for more than about 20 hours of storage in this application, leaving about 10% to 12% of annual energy to fuel. A judgment about Rondo’s use case, not a general finding about storage duration. O’Donnell
- About 300 gigawatts of brick heat storage running at blast furnaces worldwide. O’Donnell
- Ten-year interconnection queue for Oklahoma wind; seven and a half years average for new California utility-scale solar; 22% of wind projects proposed in Sweden the prior year were permitted; 2,000 hours of negative wind prices in Oklahoma. O’Donnell
07Where it’s contested
- Whether electrifying industrial heat is purely an economic problem. Kann frames it that way: nothing technical stops a factory from electrifying today. O’Donnell partly declines the framing: it is economic and also somewhat technical, because live electrification cannot reach deep decarbonization on 30% to 40% of the year’s hours.
- Grid defection. Kann offers industrial grid defection as an emerging thesis and invites agreement. O’Donnell takes half of it, agreeing about the migration of industry toward cheap wind and solar but explicitly predicting value to the grid rather than defection from it. The distinction is the guest’s own and should not be collapsed into the host’s version.
- The 20-hour ceiling is a business judgment, not a measurement. It rests on the claim that fuel backup in a boiler is about 90% efficient against about 50% for backing up the grid with a power station, and on Rondo’s target market.
- Portfolio company caveat. O’Donnell is ranking technologies, one of which his company sells, and the comparative figures are not independently sourced here. Kann does press on intermittency and on siting, and gets substantive answers.
- No prices anywhere. Striking for an episode whose stated first test is cost: no dollar figure is given for delivered heat from any option, so the ranking rests on efficiency ratios and unquantified capital costs.