Catalyst N° 030 of 125 9 Aug 2024
Understanding the transmission bottleneck
with Rob Gramlich, founder and president, Grid Strategies
In this note
The question
The United States has nearly stopped building transmission at exactly the moment it needs far more of it. What is actually blocking it, and is it fixable?
The answer
The blockage is three connected problems, and all three trace to the same root. Congestion on the existing grid, an interconnection process that has seized up, and a near-halt in new buildout are symptoms of a network with no spare capacity left and no habit of planning ahead of the generators that want to plug into it. Gramlich’s answer is that this is fixable and was in fact done recently, in Texas and the upper Midwest between roughly 2008 and 2013. His ranking of the barriers is worth noting because it is not the usual one: he puts planning and cost allocation first, and treats permitting, the subject of the political moment Kann uses to introduce the episode, as hard but solvable.
03The argument
Gramlich’s fifty-year sketch is what makes the current stall legible. The 1970s saw a large buildout to reach remote coal and hydro, laid over a network that had grown up mostly connecting roughly 3,000 independent utilities to each other for reliability. Then came decades of almost nothing, which he treats as largely defensible: load growth had run as high as 7% a year and went flat, there was surplus generation, and the gas combined-cycle wave arriving around 2000 did not need much new wire. A second real buildout ran from about 2008 to 2013, driven by wind and by two deliberate regional programs, and peaked at roughly 4,000 miles of high-voltage line in 2013 alone. Then it died again, down to a couple of hundred miles a year, under a tenth of the peak. The causes he gives for that second stall are mixed: a federal rule whose unintended consequences often get the blame, but also cheap solar, which let developers build locally instead of hauling power from remote wind, and cheap shale gas, which did the same. The distinction that matters is that the first stall happened because nobody needed the capacity, while the second happened even though the need was visible.
The three problems he and Kann work through are really one problem seen from three angles, and the connecting idea is headroom. Congestion is what happens when the network cannot deliver from one point to another: the generator at the source gets a low price, the load at the far end pays a high one, and the gap is a cost split between them. Gramlich’s firm found those congestion costs doubled in a single year, 2020 to 2021, and he expects the curve to look like a hockey stick rather than a smooth slope, because once a line is at capacity there is nothing gradual about it. Interconnection is the same scarcity expressed as process. A new generator pays not only for its own connection but for the deeper network upgrades it triggers, which he likens to being billed for a road five miles away because your new house was the straw that broke the camel’s back. That was tolerable when the grid had slack and few projects triggered anything. Now almost every project triggers something, so developers drop out rather than pay, every dropout forces a restudy of everyone behind them, and the country’s small supply of transmission engineers spends its time on restudies instead of planning the network.
Which sets up his fix, and he is candid that it is almost too obvious: plan the regional network first for the generation mix you expect, build it, and let generators connect for a zonal fee rather than a bespoke study each. He points to Texas’s Competitive Renewable Energy Zones and the Midwest’s Multi-Value Projects as proof it works, and the mechanism he emphasizes is financial rather than engineering. Those programs forecast generation, retirements and demand on a ten to twenty year view, deliberately traded off remote generation against the cost of the transmission needed to reach it rather than maximizing wire, and then spread the cost across all the beneficiaries through a regional tariff. Capital was never scarce, he says; what is scarce is a way to earn your money back on a useful line. His shorthand is three barriers, planning, permitting and paying, and his weighting within it is clear. In the Midwest program 16 of 17 lines were permitted, a batting average he says the industry can live with, and he argues most long lines run through rural land where a landowner lease is the operative negotiation rather than a town-scale fight.
He is less optimistic about everything else. Cheaper partial remedies exist, including storage placed at both ends of a constraint so it behaves like a line, and grid-enhancing technologies that push more through existing wires, and he likes them, but he names the incentive problem plainly: utilities earn on capital in the rate base, and cheap solutions do not build rate base. He agrees with Kann that nothing short of new lines stops congestion from rising. On process he expects real but bounded improvement, with interconnection times perhaps falling from about four and a half years to three, and queues at least not getting worse, and nothing better than that until lines actually get built. The two positions he holds at once are the useful takeaway: this is not rocket science and the country has done it before, and none of the policy of the preceding few years has solved it, the promising proposals have not passed, and the problem is still getting worse.
04What you need to know first
- Congestion
- Not a traffic jam in the ordinary sense but a price gap. When a line cannot carry all the power that wants to flow, the sending end clears at a low price and the receiving end at a high one. Generators lose revenue, consumers pay more, and the difference is the congestion cost.
- Interconnection and network upgrades
- Connecting a new plant involves both the short line to the grid, the gen-tie, and any reinforcements elsewhere on the network the new injection makes necessary. Under current rules the individual generator is billed for the second category, which is what makes the queue unstable.
- Cost allocation
- The rule deciding who pays for a line. Charging all the beneficiaries across a region, rather than the one generator who triggered the need, is the lever Gramlich credits for the buildouts that worked.
- Grid-enhancing technologies
- Monitoring and control equipment that gets more out of existing wires, including dynamic line ratings, topology optimization and power flow control. Fast and cheap relative to new lines.
05Details worth keeping
- The 2013 peak, roughly 4,000 miles of 345 kilovolt and above in a single year, was by his account possibly a record for at least a few decades, though he says it loosely. Current build is a couple of hundred miles a year.
- Speculative queue filings are rational rather than abusive. A developer intending one project may file six requests hoping one lands on a cheap spot. Gramlich notes his solar and wind clients resent the speculative label, and asks what else a developer is supposed to do.
- The Texas program passed around 2008 through an unusual alignment between conservative West Texas ranchers and the environmental community.
- The regional planning exercises were not maximum-transmission exercises. They explicitly looked for the sweet spot between local and remote generation, balanced against the cost of wire.
- Cheap congestion remedies run into utility economics. Rate-base returns reward capital spending, which is why grid-enhancing technologies are a harder sell than their price would suggest.
- Prospective modeling systematically understates congestion, because models assume lines are in service that in reality are not. Investors therefore find curtailment risk hard to price and, in his words, frustrating.
- Gramlich’s closing pitch is a labor pitch: the field needs many more people, across consultancies, non-profits and trade associations.
06Claims worth citing
All figures as stated in the episode released 2024-08-09. The conversation is a rerun of a 2023 interview, so treat every “current” number as a 2023 figure. Queue statistics and interconnection timelines move quickly.
- The US may need to triple high-voltage direct current transmission capacity by 2050, and to increase capacity by roughly 60% by 2030, for deep electrification. Princeton Net Zero America study, cited by Kann in the 2024 introduction
- Historic load growth ran as high as 7% a year before flattening in the later decades of the twentieth century. Gramlich
- The industry grew up with roughly 3,000 independent utilities. Gramlich
- Roughly 4,000 miles of 345 kilovolt and higher line built in 2013 alone, against a couple of hundred miles a year now, under 10% of the earlier rate. Gramlich
- Congestion costs doubled from 2020 to 2021, with the caveat that gas prices and weather add noise to any single year. Grid Strategies report, cited by Gramlich
- Interconnection used to take one to two years and now takes over four on average. Later he refers to the same figure as four and a half years, so treat it as roughly four to four and a half. Gramlich
- Interconnection costs used to sit around $100 per kilowatt. His statement of the current number is self-corrected mid-sentence and lands ambiguously, “probably over 300” and then “maybe 200 to 300,” with some locations reaching $800 to $1,000 per kilowatt. Quote the range, not a point estimate. Gramlich
- About 2 terawatts of generation sit in interconnection queues, almost all wind, solar and storage, against roughly 1.25 terawatts of generating capacity actually operating. Gramlich
- 16 of 17 lines in the Midwest Multi-Value Projects program received permits. Gramlich
- $760 million in the Inflation Reduction Act for transmission host community economic development. Gramlich
- Over 100 gigawatts a year of solar alone in the US by roughly the end of the decade, and about 80% of the Inflation Reduction Act’s carbon reductions lost if the grid is not built out. REPEAT Project, cited by Kann and Gramlich
- The federal interconnection reform proposal passed on a bipartisan 5-0 vote at the proposal stage, which is why Gramlich expects it to proceed regardless of commissioner turnover. Gramlich
07Where it’s contested
- Permitting gets demoted, against the framing. Kann introduces the episode through momentum on permitting reform, and later returns to local opposition as a death knell for past projects. Gramlich calls permitting a genuine challenge but solvable, points to 16 of 17 lines permitted, and argues most lines run where few people live, unlike siting an industrial facility in a town. This note follows him rather than the framing, but the difference in emphasis is real and the episode does not resolve it.
- The congestion doubling is one year of data with acknowledged noise. Gramlich flags gas prices and weather himself, and the hockey-stick shape he expects is a forecast rather than a measurement.
- Queue size overstates real projects and he says so. Developers file several requests per intended project, so 2 terawatts in the queue is not a pipeline of 2 terawatts of real generation.
- How much process reform can deliver. He expects interconnection timelines to improve to perhaps three years and no further without new lines, which is a judgment rather than a modeled result.
- The optimism and the alarm are held simultaneously. He says the problem is not technically hard and has been solved before, and in the same breath that it is getting worse, that recent policy has not fixed it, and that the federal regulator’s direction became uncertain after its chairman departed for reasons unrelated to electricity policy. Kann presses him to pick a point on the scale between everything is fine and everything is broken, and does not get one.