Catalyst N° 037 of 125 3 Oct 2024
DAC’s bumpy road to commercial scale
with Andreas Aepli, chief financial officer, Climeworks
In this note
The question
The first commercial direct air capture plants are running. What does it actually take to get from there to commercial scale, and what has the one company that has done it learned along the way?
The answer
Harder and slower than the models assume, and for unglamorous industrial reasons rather than scientific ones. That shapes both the financing, which has to stay equity-heavy through several deliberate 5 to 10x scaling steps before project finance becomes available, and the market, which is short of delivered tons today while simultaneously short of the long-dated contracts needed to finance the much larger plants everyone wants built.
03The argument
The concrete fact the episode turns on is a gap. Orca, Climeworks’ first plant, has a nominal capacity of 4,000 tons of carbon dioxide a year, meaning what the design would capture running at maximum efficiency. About two and a half years after starting up, it runs at roughly 2,500 to 3,000 tons. Nothing about the underlying chemistry failed. Capturing carbon at 420 parts per million, one molecule in 2,500, is genuinely hard, but that difficulty was known. What Climeworks did not know was everything that only appears when you run 24/7 in a real operating environment and owe a customer deliveries. A filter supplier’s quality varied within tolerances that were fine for that supplier’s other customers and not fine for capture efficiency measured over weeks and months. Iceland’s weather arrives as it is, with snow, hail, horizontal rain and impurities, and pre-treating incoming air is uneconomic almost immediately, which is why their chief technology officer at the time described the job as building a tractor rather than a sports car. Sequestration demands very pure carbon dioxide delivered continuously, so without a downstream purity upgrade you can end up dumping gas you already spent energy capturing. And the accounting compounds it: certification deducts the lifecycle emissions of building and operating the plant, and that deduction starts on day one, when the plant is least efficient, so the early months sell an even smaller share of what they capture.
The financing strategy is a direct consequence. Aepli argues you cannot go from pilot scale to the size at which a plant is finally profitable in one jump, because that concentrates enormous technological risk into a single very large capital commitment. Instead you take digestible steps of roughly 5 to 10x, which de-risks the technology at lower capital per lesson. Orca at 4,000 tons was followed in May by Mammoth at almost 10x, and the next plant, the first in the United States, is around 250,000 tons, another 7 to 8x. But every intermediate plant is by construction not yet profitable at its own size, which is precisely what project lenders will not fund. That is why the 2022 raise was a roughly $650 million corporate equity round rather than project debt. The eventual goal is a diversified stack of grants, project equity, project debt, tax equity and some corporate equity, and the pieces arrive gradually as proof accumulates. Climeworks did get a project finance facility done against Orca, which Aepli says was hard and had to be subsidized because Orca is not profitable at that size. For the next plant he expects allocated government grants plus project equity, with a classic project financing possibly only after the plant has proven operational stability through its ramp-up. One detail makes that more plausible than it sounds: Climeworks’ own technology is less than half the capital cost of a project, and the standard balance-of-plant equipment can carry a construction contractor’s performance wrap even when the novel part cannot.
Then the market description inverts the obvious reading. Today direct air capture looks supply-constrained, and in one sense it is: Orca and Mammoth are sold out for their expected operating lives and Climeworks is now selling the next plant. But that is not the constraint that decides whether the next plants exist. To justify a facility of 200,000 to 500,000 tons a year or larger you need offtake contracts running to millions of tons, and Aepli says he would want 10 to 15 million tons committed for a single million-ton facility. The entire market has sold 5.7 million tons so far this year. So the market is short of delivered tons and short of bankable long-dated demand at the same time, and by his account it is the second that limits how fast new plants can be committed. He expects that to flip, but he dates the flip carefully: not the 2024, 2025, 2027 or 2028 vintages, which are thin, but the 2030 and 2035 vintages, as companies come up against net-zero commitments they have to actually fulfill.
That is also why transparency functions as strategy rather than virtue. A lot of new direct air capture companies have appeared, funded in an environment where equity rewards ambitious promises, and Aepli’s fear is industry-level: if cost targets and deployment volumes are over-promised and then missed, buyers conclude the whole category promises and does not deliver. He would rather competitors deploy, hit the same learning curve, and inject what he calls a dose of reality, even though he expects some of them will not survive the step. The same logic runs through his contracting. There is no market price for removal, so pricing balances cost-plus against what buyers will pay, and Climeworks has spent about four years pushing customers toward terms that make assets financeable: five years minimum, ideally ten or fifteen, take-or-pay, clear payment terms, and assignable to the asset being financed. Customers push back, he says, because few sellers ask for any of it.
04What you need to know first
- Nominal capacity
- What a plant is designed to capture running flat out at maximum efficiency. The actual run rate is a different number, and the gap between the two is most of this episode.
- Lifecycle emissions deduction
- Certified tons sold are net of the emissions from building and running the plant. Because the deduction starts the day the plant does, an inefficient early-life plant loses a disproportionate share of its output before it can sell anything.
- Offtake agreement
- A contract to buy future output. Whether it is long, take-or-pay, creditworthy and assignable to the asset is what decides if a lender will finance the plant against it.
- Project finance versus corporate equity
- Project finance lends against one asset’s contracted cash flows and wants proven technology. Corporate equity funds the company and absorbs technology risk. Novel technology has to be paid for with the second until it has earned its way into the first.
05Details worth keeping
- Climeworks was founded in 2009 by two doctoral students as a university spin-off, funded first by friends and family, then angels, then family offices, because climate venture funds did not really exist at the time. First capture unit in 2014. First commercial pilot in 2017, selling captured carbon dioxide to Coca-Cola for use in a greenhouse.
- The Series F brought large institutional investors onto the cap table for the first time, and Aepli calls it the largest venture-type raise in Switzerland. The milestones promised for it were about a 10x scale-up, movement down the cost curve, technology improvement, and building a market for project-financeable offtake.
- The buyer pool is broadening underneath Microsoft’s dominance: other technology companies, banks including J.P. Morgan and UBS, insurers, and more recently hard-to-abate industries such as airlines, all at much smaller volumes.
- Climeworks sells portfolios as well as its own capture, blending cheaper, less permanent removal early and shifting toward higher permanence as costs fall. That lowers the average price a buyer pays while keeping them exposed to the durable end of the market.
- Contracts are fixed price with indexation rather than pure fixed price, a term Aepli says they introduced about three years ago on the reasoning that energy would be constrained rather than abundant over a twenty-year horizon. On the supply side they hedge the same risk with very long duration Icelandic energy contracts at fixed and indexed pricing.
- On intermediaries and brokers, the objection is creditworthiness rather than usefulness. They reduce friction and educate buyers, but most do not have the balance sheet of a Microsoft or a J.P. Morgan, many came from selling spot, and very few can sign agreements extending beyond 2030.
- The demand catalysts he names are guidance from the Science Based Targets initiative, which he hopes will set concrete short-term removal targets, and the early compliance markets appearing in Japan and the United Kingdom.
06Claims worth citing
All figures as stated on 2024-10-03 and roughly two years old. Plant performance, sold volumes and prices in this market move quickly; the market size figures in particular were growing several-fold a year at the time.
- Orca has a nominal capacity of about 4,000 tons a year and now runs at roughly 2,500 to 3,000 tons, reached after about two and a half years of operation. Aepli
- Orca began operating in 2021 and was the first commercial direct air capture plant in the world. (Kann; Aepli describes it as their first plant combining capture with permanent storage sold as carbon removal)
- Climeworks raised about $650 million in its Series F, completed April 2022. Aepli
- Mammoth was deployed in May, almost a 10x scale-up on Orca. The next plant is about 250,000 tons a year, a further 7 to 8x, and the first in the United States. Aepli
- Orca and Mammoth are sold out for the expected operating life of the plants. Aepli
- Globally sold volumes were about 100,000 tons at the end of 2021, about 4.6 million tons last year, and 5.7 million tons so far this year. He is describing the durable removal market Climeworks sells into but does not state the boundary precisely, so check what is counted before quoting. Aepli
- Air is about 420 parts per million carbon dioxide, roughly one molecule in 2,500. Aepli
- Climeworks’ own technology is less than 50% of the capital cost of a project. Aepli
- Plants of 200,000 to 500,000 tons a year or larger are the size that has to get built; filling a million-ton facility would want 10 to 15 million tons of offtake. Aepli
- Longest offtake signed is 15 years; the terms they push for are five years minimum, ideally 10 to 15, take-or-pay and assignable to the asset. Aepli
- Published purchase prices run from the high hundreds to low thousands of dollars a ton for direct air capture, perhaps the low hundreds for biochar, and the tens of dollars for less permanent nature-based removal. Kann, not disputed by Aepli
- Scaling in steps of roughly 5 to 10x is the strategy Aepli defends, against jumping from pilot straight to profitable scale. Aepli
- The project finance facility executed against Orca had to be subsidized because Orca is not profitable at its size. Aepli
07Where it’s contested
- The central worry is aimed at the guest’s own industry. Aepli says direct air capture still lives off promise, that there may be too many unrealistic promises about cost and deployment volumes, and that some companies will not make it to the next stage. He does not name any, and he is a competitor to the companies he is describing, which is worth holding in mind even though the self-reported figures he gives about Climeworks are unflattering ones.
- The supply-demand flip is a forecast and he dates it. Kann presses on whether demand always outruns supply or eventually reverses. Aepli’s answer is that the near vintages are thin and the constraint will bind on 2030 and 2035 volumes, which is a prediction rather than an observation.
- There is no price comparability in the market and he says so. Quality varies widely even between direct air capture sellers; some have independently certified volumes and full lifecycle deduction, others are earlier stage, need offtake badly, and come in at much lower prices they promise to customers. That is an implied criticism of peers’ accounting that he neither names nor quantifies.
- Project finance availability is hedged throughout. Not a light switch, gradual, partial, possible only for the standardized portion of a project, and the classic structure may arrive only after a plant has proven itself through ramp-up.
- No cost per ton, and no cost target, appears anywhere in the episode. For a conversation about reaching commercial scale with a chief financial officer, that is a conspicuous absence. Cost reduction is named as a Series F milestone and never quantified.