Catalyst N° 057 of 125 27 Mar 2025
The potential for flexible data centers | Catalyst
with Tyler Norris, PhD candidate, Nicholas School of the Environment, Duke University
In this note
The question
How much additional data center load could the existing US grid absorb if that load agreed to be a little bit flexible?
The answer
A great deal, on the study’s terms: up to 98 gigawatts of new data center load at half a percent curtailment, or 76 gigawatts at a quarter percent. The terms are doing heavy work. That curtailment is measured as a share of the new load’s maximum potential annual energy rather than a share of hours, the headroom is calculated against generation and historical peaks only, and transmission and distribution constraints are not modeled at all.
03The argument
The study started from a contradiction. Utility regulators in the southeast told Norris and his co-authors in the fall that they had been told data centers are 100% inflexible, so they were planning for all of it as firm load. At the same time the Secretary of Energy Advisory Board had issued recommendations on data center flexibility and the Electric Power Research Institute had launched a flexibility initiative. Both cannot be right. The question matters because the power system is sized for rare extremes, heat waves and polar vortex cold snaps, so much of it sits idle most of the time. Across the 22 largest balancing authorities, covering roughly 95% of US load, the average load factor is 53%, meaning average consumption is about half of peak consumption. In 90% of hours more than 30% of the system goes unused. If a new load could be added that simply never showed up at those extremes, the question is how much of that idle capacity it could occupy.
The method is what makes the answer defensible, and it is also where the conditions live. Norris calibrated to each balancing authority’s realized peaks over the past nine years and required that new load never push a realized peak above them, which deliberately leaves unused the reserve margin, the cushion of spare generating capacity a system carries above its peak. That choice is conservative, since the numbers would be larger if reserve margin counted; it also means the added load does not lean on the dirtiest, least efficient units. The team originally planned to model one to five percent curtailment, one to two percent being roughly what existing demand response programs ask for. The results came back so large they ran it down to 0.5% and then 0.25%. The critical thing to understand about those numbers, which Kann first restated as a share of hours before the two of them settled on the right reading, is that they are percentages of the new load’s maximum potential annual energy consumption, not percentages of hours. The model assumes the new data centers otherwise run at 100% utilization constantly. The budget is therefore energy and not hours, and it can be spent as many shallow reductions instead of a few full shutdowns, which means curtailment touches more hours of the year than the headline percentage suggests.
That distinction is what makes the ask plausible operationally. At the 0.25% setting, curtailment of some amount would be required in about 85 hours a year on average, and in 73 of those 85 hours at least half the new load is retained, in 50 of them at least three quarters. This is mostly partial dimming, not switching off. The extreme peaks themselves average two and a half to five hours, and Norris says forecasting has improved enough to see polar vortex events coming up to two weeks out, so at least the cold-snap events are short and can be anticipated. The menu of responses is correspondingly wide: defer or front-load a training run, shift workloads between data centers in different markets, lean on on-site generation or storage, or reduce cooling, which is a large share of data center draw and is conveniently not needed at full power on the winter mornings when the southeast actually peaks. Straight reduction of operations is the last resort and the one operators like least.
The catch is that the study answers the generation question and not the deliverability question. In many places the binding constraint is not whether there is enough power but whether the wires can carry it to that spot under contingency conditions. Asked how much of the 98 gigawatts survives real transmission and distribution limits, Norris said there is no way to know without running it, then under pressure offered roughly 10% erosion as a guess he immediately labeled as just him talking. Kann was audibly skeptical it could be that small. Norris’s counter is that full deliverability is an extremely strict criterion tested against conditions that are genuinely rare, and that load and generation can be connected before those upgrades are finished, which is how ERCOT, the Texas grid operator, gets generation online faster. The second catch is institutional rather than physical. This is not simply enrolling data centers in demand response, which Norris calls a simplistic reading, because existing participants were planned as firm load and opted in later for economic reasons. Doing this properly means treating the load as flexible in the planning and interconnection study itself, which is a different act by a different set of people. And the market is arranged against it: financing counterparties and owner-operators are used to firm service as the gold standard, and hyperscalers have competitive reasons not to disclose what they can actually do. The lever most likely to break that open, in Norris’s view, is an explicit trade of flexibility for a faster grid connection.
04What you need to know first
- Balancing authority
- The entity responsible for matching supply and demand across a defined chunk of the grid. The study covers the 22 largest, roughly 95% of US electricity load, and computes headroom separately for each.
- Load factor
- Average consumption divided by peak consumption. A 53% load factor means the system is on average running at about half of what it was built to deliver, which is the idle capacity this study is trying to sell.
- The curtailment metric
- Not hours. A share of the maximum energy the new load would use running flat out all year, spendable as partial reductions.
- Deliverability
- The standard that a grid connection has no bottlenecks even under contingencies with all local generators running at once. Norris calls the word a misnomer, since failing the test does not mean electrons cannot reach the load in ordinary conditions.
05Details worth keeping
- The programs that exist are thin. ERCOT has a controllable load service that makes the trade explicit. Pacific Gas and Electric’s Flex Connect works mostly at distribution scale for electric vehicle chargers, with hopes of expanding it, and Southern California Edison runs something similar. What is missing is an established published offering for large loads that says what flexibility buys you in interconnection time.
- Bridge power may solve the economics by accident. Data centers increasingly bring their own generation, often gas, to start operating before the grid connection arrives. Once the grid connection lands, that already-amortized asset can become the curtailment backstop, running a fraction of a percent of hours, which would never pencil if bought for that purpose alone. Norris agreed and said the better version is leasing, so the equipment moves on to the next customer; he described a California company building that model with trucked-in lithium-ion batteries.
- Norris pushes back on the 24-7 framing itself. Servers may run continuously, but a data center does not draw its maximum all year, and he thinks regulators have been badly confused on this point.
- Crypto mining is the most flexible large computational load on the system today, able to go from maximum draw to zero within a minute or a few minutes.
- He is explicit that none of this is an argument against building generation and transmission, which he says are needed for other loads, decarbonization and reliability regardless.
06Claims worth citing
All figures as stated on 2025-03-27. The program and deal landscape in this episode is the fastest-moving part and should be assumed stale; the study’s structural findings are more durable.
- Up to 98 gigawatts of new data center load could be added at 0.5% curtailment of that new load’s annual energy, and 76 gigawatts at 0.25%, across 22 balancing authorities representing about 95% of US load. Norris, Duke University study
- That is roughly three to five Project Stargates, the data center initiative announced by President Trump and OpenAI in January. Norris
- Average load factor across those 22 balancing authorities is 53%; in 90% of hours more than 30% of the power system sits unused. Norris
- At the 0.25% setting, curtailment would be needed in about 85 hours per year on average; in 73 of those hours at least 50% of the new load is retained, and in 50 of them at least 75%. Norris
- Extreme peak events last on the order of two and a half to five hours. Norris
- Forecasts suggest AI-specialized data centers will be the single largest driver of US load growth for the next five to seven years, with some putting data centers at about 44% of all US load growth. forecasts cited by Norris
- Existing demand response programs typically ask for peak shaving in the range of 1% to 2%. Norris
- Roughly 10% of the 98 gigawatts might be eroded by transmission and distribution constraints. Norris volunteered this only under pressure and called it a very rough first-order estimate, “just me talking.” Treat it as a guess, not a finding. Norris
- Data center utilization rates in circulation differ sharply: Lawrence Berkeley National Laboratory’s congressionally mandated December report used 50%, while the Energy Information Administration and E3 have used numbers closer to 85%. cited by Norris
- Existing operating data center load on the US grid is under 30 gigawatts. Kann, who explicitly said he did not know the exact current number
- Duke Energy said at a public event the week before recording that it will require all new hyperscale loads above 100 megawatts to participate in demand response. Norris described himself as quite surprised by it. Duke Energy public statement, reported by Norris
07Where it’s contested
- The deliverability gap is the study’s biggest open question and the guest says so. The model constrains against generation and historical peaks, not against transmission and distribution. Norris declined to quantify it, then gave 10% as an off-the-cuff figure, and Kann pushed back that it sounded low. Anyone repeating the 98 gigawatt number without this caveat is repeating a generation-side headroom estimate as though it were a buildable number.
- The host restated the core metric incorrectly at first. Kann described the curtailment as a percentage of hours in which the data center would shut off. Norris half-agreed and then restated it as a share of maximum potential annual energy use, and Kann drew the distinction himself a moment later. The two are not interchangeable: an energy budget can be spent across many partly curtailed hours, so curtailment is called on in more hours than the percentage suggests, while each of those hours is usually only a partial reduction.
- Conservatism runs in both directions. Excluding reserve margin makes the number smaller than it could be; omitting transmission constraints, and limits on how fast generation and load can move from hour to hour, makes it larger. Norris names both and does not claim the errors cancel.
- Whether operators will actually take the deal is untested. Hyperscalers and colocation developers publicly maintain they are not flexible; Norris thinks they are underdisclosing deliberately, both to keep negotiating leverage and to hide capability from competitors. Financing counterparties are accustomed to firm service. His expectation that faster interconnection will be the wedge, and that flexibility deals will then spread beyond speed to power, is a forecast about market psychology, not a modeled result. He notes the live negotiations are bilateral and confidential, so the evidence is thin by construction.
- This is not just demand response with a new name. Kann floated that shorthand; Norris called it simplistic and drew the distinction between load that was planned firm and opted in later versus load planned as flexible from the interconnection study onward.
- Kann calls it harder than it sounds and explicitly not a panacea in his opening, and the episode never resolves whether the regulatory and contractual machinery to capture this headroom can be built.